An agency was entitled to cancel a solicitation when its needs changed–even though the anticipated changes in its needs “might be characterized as minimal.”

In a recent bid protest decision, the GAO confirmed that a procuring agency has broad discretion to cancel a solicitation when the agency’s anticipated needs change, and that discretion extends to cases in which the agency’s changed needs could be addressed by amending the existing solicitation.

The GAO’s decision in Social Impact, Inc., B-412655.3 (June 29, 2016) involved a USAID solicitation for support for the agency’s Monitoring, Evaluation, and Learning Program in Tanzania.  After evaluating competitive proposals, USAID initially selecting Management Systems International for award.  Social Impact, Inc. then filed a GAO bid protest, challenging the award to MSI.

In response to the protest, USAID notified the GAO that it intended to terminate the award to MSI and cancel the solicitation.  Explaining its decision to cancel the solicitation, the agency stated that “Changes in USAID/Tanzania Mission staffing, and its in-house capacity, as well as changes in Agency experience and best practices vis-a-vis monitoring, evaluation, and learning (MEL) activities, dictate that the Mission streamline its MEL activities by moving some of the underlying procurement’s related work, such as the learning component, in-house to maximize efficiency and cost-savings.”

Social Impact filed a GAO bid protest challenging the agency’s decision to cancel.  Social Impact argued, in part, that the cancellation was inconsistent with FAR 15.206(e), which states:

If, in the judgment of the contracting officer, based on market research or otherwise, an amendment proposed for issuance after offers have been received is so substantial as to exceed what prospective offerors reasonably could have anticipated, so that additional sources likely would have submitted offers had the substance of the amendment been known to them, the contracting officer shall cancel the original solicitation and issue a new one, regardless of the stage of the acquisition.

Social Impact contended that the changes in USAID’s needs were minimal, and not “so substantial as to exceed what prospective offerors reasonably could have anticipated.”  Therefore, Social Impact argued, USAID should have amended the existing solicitation rather than canceling it.

The GAO wrote that “Section 15.206(e) mandates that an agency cancel a solicitation and issue a new one” when the “so substantial” test is satisfied.  “There is nothing to suggest, however, that the converse is true, i.e., that an agency is is prohibited from canceling a solicitation when changes in the agency’s requirements do not rise to the level contemplated in Section 15.206(e).”  The GAO continued:

To the contrary, our Office has held that, even when the changes could be addressed by an amendment, “[t]he only pertinent inquiry is whether there existed a reasonable basis to cancel, since an agency may cancel at any time when such a basis is present.”  Where the record reflects a reasonable basis to cancel, and in the absence of the criteria described in section 15.206(e), the agency has broad discretion in determining whether to cancel or amend a solicitation.

The GAO concluded that “we find the agency’s decision to cancel the solicitation to be reasonable despite the fact that the anticipated changes to the solicitation might be characterized as minimal.”  The GAO denied Social Impact’s protest.

As the Social Impact case demonstrates, agencies enjoy broad discretion when it comes to canceling solicitations.  Even where an anticipated change in the agency’s needs could be satisfied by amending the existing solicitation, the agency may validly decide instead to cancel it.