No Protest of CIO-SP3 SB Order Below $10 Million, Says GAO

A CIO-SP3 SB contract holder could not protest the award of a task order to a competitor because the order was valued at less than $10 million.

In a recent bid protest decision, the GAO confirmed that civilian task order awards–including those under CIO-SP3 SB–generally cannot be protested unless the value of the order exceeds $10 million.

Continue reading

GAO Confirms: No Protests of Most Subcontract Awards

Despite older case law to the contrary, the GAO ordinarily lacks jurisdiction to decide a protest challenging the award of a subcontract, even where the subcontract is alleged to have been made “for” the government, as in the case of some subcontracts awarded by DOE Management and Operation prime contractors.

In a recent decision, the GAO confirmed that, except in very narrow circumstances, it won’t decide protests challenging subcontract awards.

Continue reading

GAO Confirms: DoD Task Order Protest Threshold Is $25 Million

The GAO ordinarily lacks jurisdiction to consider a protest of a task or delivery order under a DoD multiple-award contract unless the value of the order exceeds $25 million.

In a recent bid protest decision, the DoD confirmed that the 2017 National Defense Authorization Act upped the jurisdictional threshold for DoD task orders from $10 million to $25 million.

Continue reading

Sorry: No GAO Protests of U.S. Mint Procurements

As a branch of the Treasury Department, the United States Mint would usually be subject to federal procurement laws, like bid protests. As one contractor recently discovered, however, certain activities at the Mint have been exempted from many federal procurement laws, including GAO protest review.

Simply put, the GAO can’t decide a bid protest of Mint procurements.

Continue reading

Reminder: No Ostensible Subcontractor Protests At GAO

The GAO lacks jurisdiction to consider a challenge to a contract awardee’s size status, including questions of whether the awardee is affiliated with its subcontractor under the ostensible subcontractor rule.

In a recent bid protest decision, the GAO confirmed that it will not adjudicate an allegation of ostensible subcontractor affiliation.

Continue reading

No Protest Of Terminated Task Order, Court Says

A contractor could not file a valid bid protest challenging an agency’s decision to terminate the contractor’s task order, according to the U.S. Court of Federal Claims.

In a recent decision, the Court agreed with the GAO, which also held that the contractor’s challenge involved a matter of contract administration–something outside the bid protest process.

Continue reading

GAO’s Civilian Task Order Jurisdiction Restored

GAO’s jurisdiction to hear protests of certain civilian task and delivery orders has been restored.

On December 15, 2016, the President signed the 2016 GAO Civilian Task and Delivery Order Protest Authority Act (the “ 2016 Act”) into law.  The 2016 Act restores GAO’s recently-expired jurisdiction to hear protests of civilian task and delivery orders valued in excess of $10 million.