Winding Down: COVID-19 Work Stoppages & Suspensions

Many contractors are facing work stoppages or suspensions because of COVID-19—especially where working from home is not feasible. This post aims to provide a little bit of clarity about work stoppages, suspensions, and the FAR’s excusable delays provision.

Continue reading

COFC Rejects Agency’s Basis for Default Termination

The Court of Federal Claims recently reversed an agency’s default termination of a contractor that had experienced numerous performance issues and delays. The agency claimed that performance was “incurably behind schedule,” despite the contractor’s proposed recovery schedule.

The court held that the agency lacked a reasonable belief that the contract could not be timely completed.

Continue reading

ASBCA Awards Costs Incurred Before Notice to Proceed

Your newly awarded government contract requires you to move significant amounts of equipment prior to receiving a Notice to Proceed (NTP). You spend thousands of dollars moving equipment and people into place so you are ready to perform once the NTP is issued. But what if instead of issuing the NTP the agency cancels your contract? Are you out all of the costs incurred to prepare for the NTP?

Not necessarily. The Armed Services Board of Contract Appeals recently reviewed just this situation and awarded a significant amount to the contractor.

Continue reading

Claim of Bad Faith Termination by Government Requires Strong Evidence, says CBCA

An agency has broad discretion to terminate a contract for convenience. But sometimes, a contractor will challenge the termination for convenience by arguing that the agency acted in bad faith in terminating the contract.

A recent CBCA decision looks at what type of evidence is needed to establish bad faith. Not surprisingly, the CBCA confirms that the standard of proof is quite high.

Continue reading

Termination For Default: The “No Reasonable Likelihood” Standard

Sometimes you may find yourself running late. It happens to the best of us for a multitude of reasons. But what happens to federal contractors when they are running late in performing under a contract and there is “no reasonable likelihood” of timely performance?

Unfortunately for contractors in this position, as illustrated by a recent Civilian Board of Contract Appeals (CBCA) decision, the result may be a default termination.

Continue reading

No Protest Of Terminated Task Order, Court Says

A contractor could not file a valid bid protest challenging an agency’s decision to terminate the contractor’s task order, according to the U.S. Court of Federal Claims.

In a recent decision, the Court agreed with the GAO, which also held that the contractor’s challenge involved a matter of contract administration–something outside the bid protest process.

Continue reading

ASBCA: Government Properly Terminated Contractor for Preliminary Finding of SCA Violation

The government can terminate a contract when the Department of Labor has made a preliminary finding of non-compliance with the Service Contract Act, even if the contractor has not exhausted its remedies fighting or appealing the finding.

The 3-0 (unanimous) decision by the Armed Services Board of Contract Appeals in Puget Sound Environmental Corp., ASBCA No. 58828 (July 12, 2016) is troubling because it could result in other contractors losing their contracts based on preliminary DOL findings–perhaps even if those preliminary findings are later overturned.

Continue reading