ASBCA: Claim Must Include Request for “Final Decision”

As readers of this blog might know, the government contracts claims process is set by statute and includes a number of requirements, such as being certified if the dollar amount is over $100,000.

But a possibly lesser-known requirement is that, in order to be valid, a claim must request that the contracting officer issue a “final decision” on the claim. In a recent decision, the Armed Services Board of Contract Appeals opined on this requirement.

Continue reading

Contracting Officer’s Death Didn’t Waive Claim Requirement

A Contracting Officer’s death did not waive the requirement that a contractor file a claim with the agency before bringing its claim to federal court.

In a recent decision, the Court of Federal Claims held that a contractor was not entitled to forego the claim requirement because of the Contracting Officer’s death–even though the agency did not appoint a replacement.

Continue reading