Is A Lease A CDA “Contract?” Federal Circuit Says Yes

Although a lease may be a “contract” in common parlance, does a lease qualify as a contract under the Contract Disputes Act?

The answer is important, because the Contract Disputes Act provides jurisdiction for the Court of Federal Claims and Board of Contract Appeals to decide challenges to contracting officers’ final decisions.  If a lease isn’t a contract under the Contract Disputes Act, government lessors could be in a bind.

The United States Court of Federal Claims recently decided the issue–and came down on the side of lessors, at least under the facts at hand.

Continue reading

Release of Claims: Contractor Signatory Must Have Authority

What goes around, comes around.

The government sometimes refuses to pay a contractor for a modification when the government official requesting the modification lacks appropriate authority.  But contractual authority isn’t a one-way street benefiting only the government.  A recent decision by the Armed Services Board of Contract Appeals demonstrates that a contractor may not be bound by a final waiver and release of claims if the individual signing on the contractor’s behalf lacked authority.

Continue reading

Termination For Default: The “No Reasonable Likelihood” Standard

Sometimes you may find yourself running late. It happens to the best of us for a multitude of reasons. But what happens to federal contractors when they are running late in performing under a contract and there is “no reasonable likelihood” of timely performance?

Unfortunately for contractors in this position, as illustrated by a recent Civilian Board of Contract Appeals (CBCA) decision, the result may be a default termination.

Continue reading

Excusable Delay: Government’s Failure To Extend Was “Constructive Acceleration”

Federal contractors not so infrequently find themselves in a position where they are unable to complete performance of a contract by the agreed-upon deadline. So, what happens when the delay is neither party’s fault, but the government denies extension of the period of performance or provides inadequate extensions?

In IAP Worldwide Services, Inc. (ASBCA Nos. 59397, 59398, and 59399), the Armed Services Board of Contract Appeals found under the legal theory of “constructive acceleration” that the U.S. Army Corps of Engineers was liable for extra costs incurred by IAP due to the Corps insistence of timely contract delivery despite excusable delays.

Continue reading

Government Tenant Liable For Damaging Leased Space

A government agency was liable for damaging leased space, even though the lease didn’t contain an explicit clause requiring the government to repair the space.

In a recent decision, the Civilian Board of Contract Appeals held that the VA was required to compensate the landlord for damage to the space, because every lease–including those entered by government tenants–contains an implied provision requiring the tenant not to damage the leased space, except for ordinary wear and tear.

Continue reading

Contractor Awarded $31,000 In Attorneys’ Fees For $6,000 Claim

A contractor was awarded more than $31,000 in attorneys’ fees and costs after a government agency unjustifiably refused to pay the contractor’s $6,000 claim–forcing the contractor to go through lengthy legal processes to get reimbursed.

A recent decision of the Civilian Board of Contract Appeals is a cautionary tale for government contracting officials, a few of whom seem inclined to play hardball with low-dollar claims, even when those claims are entirely justified.

Continue reading

ASBCA Says Contractor Wasn’t Exempt From State Tax

They say that two things in life are guaranteed – death and taxes – and status as a federal contractor may not exempt one from the latter, according to a recent Armed Services Board of Contract Appeals decision.

In Presentation Products, Inc. dba Spinitar, ASBCA No. 61066 (2017), the ASBCA held the contractor was liable to pay a state tax, and the government had no duty to reimburse the contractor. The problem arose from the fact that the contractor did not incorporate state tax costs into its proposed price, despite being required to pay the taxes under the terms of the contract and applicable state law.

Continue reading