Federal Court Again Says Agency Erred By Not Clarifying Proposal Errors

A procuring agency erred by failing to seek clarification of obvious errors in an offeror’s proposal, according to a recent ruling by the U.S. Court of Federal Claims.

In Level 3 Communications, LLC v. United States, No. 16-829 (2016), the Court held that although a Contracting Officer has discretion over whether to seek clarification of a proposal, this discretion is not unlimited. By failing to clarify obvious errors, the Contracting Officer’s decision was arbitrary, capricious, and an abuse of discretion.

The decision builds on a 2013 case, BCPeabody Construction Services, Inc., No. 13-378C (2013), in which the Court reached a similar conclusion. But so far, the GAO has drawn a hard line, essentially holding that an agency’s discretion in this area is unlimited.

Continue reading

Contracting Officer’s Death Didn’t Waive Claim Requirement

A Contracting Officer’s death did not waive the requirement that a contractor file a claim with the agency before bringing its claim to federal court.

In a recent decision, the Court of Federal Claims held that a contractor was not entitled to forego the claim requirement because of the Contracting Officer’s death–even though the agency did not appoint a replacement.

Continue reading