CORs Weren’t Authorized To Order Additional Work–So Contractor Goes Unpaid

A contractor’s performance of extra work outside the scope of the contract may go uncompensated if a contractor does not receive appropriate authorization in accordance with the contractual terms.

A Court of Federal Claims decision reinforced that a contractor should only perform work required under the terms of the federal contract or directed by an authorized government agent in accordance with the contractual terms. And importantly, a Contracting Officer’s Representative isn’t always authorized to order additional work–even if that person acts as though he or she has such authority.

Continue reading

ASBCA Says Contractor Wasn’t Exempt From State Tax

They say that two things in life are guaranteed – death and taxes – and status as a federal contractor may not exempt one from the latter, according to a recent Armed Services Board of Contract Appeals decision.

In Presentation Products, Inc. dba Spinitar, ASBCA No. 61066 (2017), the ASBCA held the contractor was liable to pay a state tax, and the government had no duty to reimburse the contractor. The problem arose from the fact that the contractor did not incorporate state tax costs into its proposed price, despite being required to pay the taxes under the terms of the contract and applicable state law.

Continue reading

Contractor’s Lackadaisical Proposal Preparation Sinks Its Claim for Costs

To federal construction contractors, the true legwork may seem to begin only after the government has accepted a proposal and performance has begun. However, a recent Armed Services Board of Contract Appeals decision reinforces that federal construction contractors’ work often should begin long before contract award.

In Zafer Construction Company, ASBCA No. 56769 (2017), the ASBCA rejected a construction contractor’s allegations of unilateral mistake, unconscionability, and differing site conditions (among other claims for additional costs). The problem? The contractor did not attend a government scheduled site visit, conduct an independent site visit, review technical drawings, submit any inquiries during the proposal stage, or otherwise take reasonable steps necessary to better ascertain the nature of the work prior to submitting a multimillion dollar proposal on a complex project.

Continue reading

Government Liable For Negligent Estimate, Court Rules

The government’s use of specifications within a contract carries an implied warranty that the specifications are free from errors. When a contractor is misled by the erroneous specifications, the contractor may seek recovery through an equitable adjustment to the contract. But what happens when the government seeks services through a requirements contract and is simply negligent in estimating its needs?

A recent Federal Circuit decision, Agility Defense & Government Services, Inc., v. United States, No. 16-1068 (Fed. Cir. 2017)  finds that a contractor may be able to recover damages in such instances under a negligent estimate theory.

Continue reading

“In Scope” vs. “Out of Scope” Modifications: GAO Explains The Difference

An agency may modify a contract without running afoul of the Competition in Contracting Act, so long as the the modification is deemed “in scope.” An “out of scope” modification, on the other hand, is improper–and may be protested at GAO.

In a recent bid protest decision, GAO denied a protest challenging an agency’s modification of a contract where the modification was within scope and of a nature that competitors could have reasonably anticipated at the time of award. In its decision, GAO explained the difference between an in scope and out of scope modification, including the factors GAO will use to determine whether the modification is permissible.

Continue reading

CBCA Orders a Federal Contractor to Play the “Waiting” Game

When issues arise in performance of a federal contract, a contractor may seek redress from the government by filing a claim with the contracting officer. However, commencing such a claim may result in an exercise of patience and waiting by the contractor.

The Contract Disputes Act, as a jurisdictional hurdle for claims over $100,000, requires a contractor to submit a “certified claim” to the agency. The CDA also requires the contracting officer, within sixty days of receipt of a certified claim, to issue a decision on that claim or notify the contractor of the time within which the decision will be issued.

That second part of the equation can lead to some frustration on the part of contractors. As seen in a recent Civilian Board of Contract Appeals decision, a contracting officer may, in an appropriate case, extend the ordinary 60-day time frame by several months.

Continue reading

Government References Didn’t Complete PPQs? “Too Bad,” Says GAO

Federal contractors frequently find themselves in the position of needing to establish their past performance credentials to secure future contracts – the government’s form of a reference check. The government often performs these reference checks by requesting completed past performance questionnaires, or PPQs, which the government uses as an indicator of the offeror’s ability to perform a future contract.

But what happens when a contractor’s government point of contact fails to return a completed PPQ? As a recent GAO decision demonstrates, if the solicitation requires offerors to return completed PPQs, the agency need not independently reach out to government officials who fail to complete those PPQs.

Continue reading