GAO Reaffirms Agencies’ Broad Discretion to (Not) Consider Price Realism for Fixed-Price Contracts

We are quickly approaching our 1000th blog post on the SmallGovCon blog. To celebrate we want to reward one lucky reader with a free one hour custom webinar for up to 50 people presented by Steven Koprince on the government contracting topic of your choice! You can enter by using the hashtag #SGC1000 on Twitter or Facebook just by telling us why you read the blog or what you love most about. You can also simply fill out this form to be entered. Good Luck!


As a general rule, an agency is only required to evaluate a fixed-price offer for reasonableness (that is, whether the price is too high). Agencies are not required to evaluate fixed-price offers for realism (that is, whether the price is too low) and, in fact, cannot do so unless the solicitation advises offerors that a realism evaluation will be conducted.

GAO recently reaffirmed this principle when it denied a protest challenging an agency’s refusal to consider the realism of offerors’ fixed prices as part of a corrective action, even though the agency suspected that at least one offeror’s price was unrealistically low.

Continue reading

Government “Poaches” Contractor’s Employee, Then Rejects Fixed-Price Invoices

Picture this scenario: the government hires your company to do a job; you assign one of your best employees to lead the effort. He or she does such a good job that the government hires your employee away. The government then drags its feet on approving your proposed replacement and refuses to pay you for the time when the position was not staffed–even though the contract was fixed-price.

The scenario is exactly what happened to a company called Financial & Realty Services (FRS), and according to the Civilian Board of Contract Appeals, FRS wasn’t entitled to its entire fixed-price contract amount.

Continue reading

GAO: No Protest Under Omitted FAR Clause

A would-be protester had no valid basis to allege agency wrongdoing when the protester’s allegation was that the awardee would violate a FAR performance of work clause–but the clause was not included in the solicitation.

In a recent decision, the GAO held (unsurprisingly), that a protester could not challenge the awardee’s supposed failure to comply with FAR 52.236-1 because the clause was omitted from the solicitation.

Continue reading

GAO: If Price Realism Will Be Evaluated, Offerors Must Be Notified

Agencies must notify offerors when price realism will be evaluated under a fixed price solicitation.

Recently, the GAO sustained a protest where a procuring agency rejected an offeror’s proposal because the offeror’s quoted prices were significantly lower than the government’s estimate–even though the solicitation did not notify offerors that price realism would be evaluated.

Continue reading

Price Realism Evaluation: Only If Solicitation Says So

An agency awarding a fixed-price contract can only evaluate offerors’ proposals for price realism–that is, determine whether offerors’ proposed pricing is so low as to be unrealistic–if the solicitation calls for a price realism evaluation.

In a recent bid protest decision, the GAO confirmed that when a fixed-price solicitation does not advise offerors that a price realism evaluation will be conducted, the agency is not permitted to reject an offeror’s proposal because of unrealistically low pricing.

Continue reading

Price Realism: Agency Erred By Failing To Conduct Analysis

An agency erred by failing to conduct a price realism analysis for a time-and-materials contract with fixed-price fully-burdened labor rates.

In a recent bid protest decision, the GAO acknowledged that a solicitation of this type does not always require that the agency engage in a price realism analysis, but found that the terms of the particular solicitation called for such an analysis–and that the agency acted unreasonably by ignoring the solicitation’s requirement.

Continue reading