Including Dollar Amount in Claim “Sum Certain”-ly Serious Business

In a recent case, the Armed Services Board of Contract Appeals, dismissed a claim for lack of jurisdiction because it did not include a “sum certain.”

The case is a good reminder of the importance of demanding a specific sum of money for most claims.

Continue reading

ASBCA: Under FAR, “Days” Meant Calendar Days, Not Business Days

The period of performance under a government contract, measured in “days,” meant calendar days–not business days, as the contractor contended.

In a recent decision, the Armed Services Board of Contract Appeals applied the FAR’s general definition of “days” in holding that a contractor had not met the contract’s performance schedule.

Continue reading

DoD Micro-Purchase Increase Is Now In Effect

The increase to DoD’s micro-purchase threshold mandated by the 2017 National Defense Authorization Act is now in effect.

A Class Deviation issued earlier this month provides, effective immediately, that the DoD micro-purchase threshold is $5,000 for many acquisitions.

Continue reading