When multiple unsuccessful offerors protest a solicitation, the GAO ordinarily will dismiss any and all bid protests associated with the procurement in the event one unsuccessful offeror takes its case to federal court–even if some protesters would prefer to remain at the GAO.
As one federal contractor recently learned in Colleague Consulting, LLC—Reconsideration, B-413156.18 (Sept. 12, 2016), the GAO’s jurisdictional rules prevent it from deciding protests when the outcome of the protest could be affected by a pending federal court decision.