PPQs Submitted Late? “No Problem,” Says GAO–At Least In One Case

While being fashionably late to a party may give the impression that one is a busy and popular person that was held up with other business, being fashionably late in federal contracting will typically have dire consequences.

However, a recent GAO bid protest decision demonstrates that when providing completed past performance questionnaires, or PPQs, being fashionably late may be acceptable – at least when the references were submitted directly by government officials, rather than the offeror.

Continue reading…

SmallGovCon Weeks In Review: November 20-December 1, 2017

As we step into December, I am looking forward the 2017 National Veterans Small Business Engagement conference next week. The NVSBE is one of my favorite annual government contracting events.  If you’ll be in St. Louis next week, please stop by the Koprince Law LLC booth to say hello.

SmallGovCon Week in Review took a break last week for the Thanksgiving holiday, so today’s edition covers government contracting news and notes from the past two weeks.  In this edition, several companies have protested the GSA’s recent Alliant 2 awards, two whistleblowers receive a big payout after uncovering procurement fraud, GAO bid protests declined in 2017 (while the effectiveness rate of protests went up), and much more.

Continue reading…

GAO Suspends Protester–Again–For “Abusive Litigation Practices”

The GAO has suspended a protester for “abusive litigation practices,” for the second time.

Last year, the GAO suspended Latvian Connection LLC from participating in the GAO bid protest process for one year, after the firm filed 150 protests in the course of a single fiscal year.  Now, citing “derogatory and abusive allegations,” among many other concerns, the GAO has re-imposed its suspension–this time, for two years.

Continue reading…

GAO: Agencies May Consider Outside Past Performance Information

When an agency requests that offerors provide past performance references, the agency ordinarily is not precluded from considering outside past performance information.

In a recent bid protest decision, the GAO confirmed that an agency’s past performance evaluation may include information outside the past performance references submitted by the offeror–and the agency can use any negative past performance information to downgrade the offeror’s score.

Continue reading…

Federal Court Interprets SDVOSB “Unconditional Ownership” Less Strictly Than SBA

The Court of Federal Claims recently issued an opinion that defines “unconditional ownership” of an SDVOSB in a more relaxed manner than the SBA, creating a split of authority on the issue.

The Court, rejecting SBA precedent, held that certain restrictions on ownership of an SDVOSB by a service-disabled veteran are acceptable under the SBA’s unconditional ownership regulations. In particular, the SDVOSB company can retain a right of first refusal that would allow it to purchase the shares of the veteran upon death, incompetency, or insolvency, and that right does not result in a violation of the unconditional ownership requirement.

With the Court and the SBA’s administrative judges staking out different positions, what should SDVOSBs do?

Continue reading…