SBA OHA: Contractors, Check Your Email Carefully (Or Else)

Everyone has that one friend who has an inbox overflowing with emails. You know the one who just can’t seem to delete any old emails, or go through and sort the legit emails from junk.  Well, when it comes to size protests and appeals, government contractors may want to be extra vigilant about checking their email inboxes and spam folders, just in case an important government email arrives.

In a recent decision, the SBA Office of Hearings and Appeals found that the size appeal clock started ticking on the day that the SBA sent an email to a contractor–even though the contractor did “not recall” receiving the email.

Continue reading

GSA Schedule Debriefing Doesn’t Extend Protest Time Frame, GAO Says

You’ve submitted a great proposal, but then you get the bad news – you lost. As most seasoned contractors know, an unsuccessful offeror often can ask for a debriefing from the agency and in doing so, hopefully get some valuable insight into its decision-making process. Many also understand that the benefits of asking for a debriefing may include extending the timeline for filing a GAO bid protest.

But not all solicitations are subject to the same debriefing regulations, and depending on how the procurement was conducted, an offeror might not be entitled to that extended deadline–as one company recently learned the hard way in the context of a GSA Schedule procurement.

Continue reading

GAO: Late Is Late–Even If Agency Server Malfunctions

You’ve hit send on that electronic proposal, hours before the deadline and now you can sit back and feel confident that you’ve done everything in your power – at least it won’t be rejected as untimely – right?

Not so fast. If an electronically submitted proposal gets delayed, the proposal may be rejected–even if the delay could have been caused by malfunctioning government equipment. In a recent bid protest decision, the GAO continued a recent pattern of ruling against protesters whose electronic proposals are delayed. And in this case, the GAO ruled against the protester even though the protester contended that an agency server malfunction had caused the delay.