Incumbent Not Entitled to “Extra Credit” in Transition Evaluation, GAO Says

An incumbent contract wasn’t entitled to receive “extra credit” in the agency’e evaluation of offerors’ transition plans.

In a recent bid protest decision, the GAO held that the agency reasonably awarded a non-incumbent more strengths than the incumbent in the evaluation of transition plans, writing that incumbency alone doesn’t automatically entitle the incumbent to the highest-possible transition plan score.

Continue reading

At GAO, Challenge of Restrictive Terms of Solicitation Tough Burden to Meet

How does a company go about challenging overly restrictive terms in a solicitation? In order to make such a challenge (and some of them do succeed), it is necessary to show something more than just the fact that a protestor cannot meet the terms of the solicitation.

A recent GAO decision provides a real-world example of how not to challenge a solicitation as overly restrictive of competition and reinforces that this can be a difficult thing to prove at GAO.

Continue reading

Late Bid Revision Costs Bidder The Award

When a bidder submits a bid under a sealed bid procurement, it is responsible for ensuring that the bid is timely submitted. But what happens if a bidder wants to revise a bid that’s already been submitted?

As a recent GAO case shows, even a revised bid must be timely submitted in order for it to be considered. If a bidder tries to revise its bid too late in the process, it might end up costing itself the award.

Continue reading

GAO Releases Updated Bid Protest Guide

Coinciding with the May 1, 2018 requirement that GAO bid protests be filed using the new Electronic Protest Docketing System, the GAO has released an updated version of its “Descriptive Guide” to the GAO bid protest process.

This Guide–the tenth edition published by GAO–is packed with useful information and tips about using EPDS and about the protest process in general.

A few EPDS-specific highlights follow.

Continue reading

GAO: Task Order Outside Scope of Underlying IDIQ Not Allowed

As agencies look for ways to streamline acquisitions, task and delivery order procurements are becoming increasingly popular. But an agency doesn’t have unfettered discretion to award work under a multiple-award contract; each task or delivery order must be within the scope of the awarded IDIQ.

A recent GAO opinion considers what happens when an agency issues task orders that are outside the scope of the underlying multiple-award contract.

Continue reading

GAO Clarifies Competition Standards for Simplified Acquisitions

A recent GAO decision has shed light on the question of what an agency must do to adequately promote competition during a simplified acquisition.

There is still no bright line for determining which agency actions meet this threshold.  However, the recent decision in Bluehorse Corp., B-415641 et al. (Feb. 6, 2018), established that merely inquiring about a solicitation, without taking further action as recommended by the procuring agency, is not enough to force an agency to include a company in a limited competition.

Continue reading

Weaknesses Cannot Be Assigned Unequally, GAO Confirms

An unequal evaluation can get an agency into hot water and force a reevaluation, as GAO has stated before. But with agencies entitled to broad discretion in their evaluations, how do you know what constitutes unequal evaluation?

Some GAO opinions can leave you wondering where the line is drawn, but a recent GAO decision provides an easy-to-understand example involving a requirement to train personnel under certain regulations. In that case, the GAO held that it was improper for the agency to assign a weakness to the protester for omitting a discussion of certain regulations as applied to its training program, while failing to assign weaknesses to several awardees whose proposals also omitted this discussion.

Continue reading