Under FAR Part 16 Task Order Solicitation, Agency Can Establish Competitive Range Without Notification

Under FAR Part 15 negotiated procurements, an agency must give notice and an opportunity to request a debriefing to offerors eliminated from the competitive range. But the notice requirement does not apply for task and delivery order procurements under FAR Part 16 where FAR Part 15 is inapplicable.

A recent GAO decision highlights this distinction.

Continue reading

GAO: Agency Closing Time is 4:30 p.m., not 5:00 p.m.

Unless an agency designates different business hours, the FAR says that a government agency is deemed to close at 4:30 p.m. local time–not 5:00 p.m., as it would be easy to assume.

In a recent case, the 4:30 p.m. closing time cost an unsuccessful offeror a chance at a GAO protest because the offeror’s debriefing request, sent to the agency at 4:59 p.m., was deemed untimely.

Continue reading

Bid Protest Filed After “Non-Required” Debriefing Was Untimely, Says GAO

GAO’s bid protest regulations provide strict timelines for filing a protest.

Typically, a protest challenging an award must be filed within 10 days after the basis of the protest is known or should have been known. There is an exception to this rule for protests filed after a debriefing, but only when a debriefing was required by the FAR. As one contractor recently discovered, where a debriefing is not required, GAO’s bid protest regulations are not nearly as forgiving.

Continue reading

DoD Immediately Implements Portion of Enhanced Debriefing Requirements

The DoD has issued a class deviation to immediately implement part of the the enhanced debriefing requirements mandated by the 2018 National Defense Authorization Act.

In a class deviation issued on March 22, 2018, the DoD says that, effective immediately, contracting officers must comply with new requirements allowing unsuccessful offerors to submit questions–and postponing the ticking of the “protest clock” until after answers are received.  But the class deviation doesn’t fully implement the 2018 NDAA’s enhanced debriefing requirements; the portion of the statute calling for the disclosure of redacted source selection information is not addressed.

Continue reading

Small Business GAO Bid Protests Are Less Successful, RAND Study Says

GAO bid protests filed by small businesses are (statistically speaking) less likely to succeed than protests filed by large contractors, according to the RAND Corporation’s recent bid protest study.

The disparity isn’t the result of discrimination against small businesses, but rather a product of other factors: primarily, the motivation to protest, the understanding of the protest system, and access to legal counsel.  RAND raises an important point, but offers no fair and easy solution.  Perhaps, given that protests overall are “exceedingly uncommon,” a solution isn’t needed–but it’s wise to think about whether there are ways to help small businesses become better educated about bid protests.

Continue reading

Bid Protest Report Gives Insight into COFC Protests

When we write about bid protest decisions on SmallGovCon, odds are that we’re writing about a GAO decision. For good reason: GAO is the most common forum protesters bring bid protests.

But SmallGovCon readers also know there’s another possible forum for protests: the Court of Federal Claims.

The GAO publishes an annual bid protest report with statistics about the number and effectiveness rate of protests, among other things. But until very recently, we didn’t have much hard data about the frequency and efficacy of COFC protests. The recently-released RAND bid protest report changed that, by including a deep dive on DoD bid protests at COFC.

Let’s take a look.

Continue reading

DoD Bid Protests Are “Exceedingly Uncommon,” New Study Finds

Only a very small percentage of DoD contracts–0.3 percent, to be precise–are protested, according to a comprehensive and fascinating new report on bid protests issued by the RAND Corporation.

The detailed report, which was prepared at the behest of Congress, concludes that DoD bid protests are “exceedingly uncommon,” and typically aren’t frivolous.  RAND’s analysts urge policymakers to carefully consider the data when evaluating whether reforms to the bid protest process are necessary–and to “avoid drawing overall conclusions or assumptions about trends from one case when it comes to the efficacy of the bid protest system.”