Government’s Delayed Response Breached Contract, Says ASBCA

Here’s a situation my colleagues and I see with some frequency: a contractor, in the course of working on a government contract, submits a request of some sort to the agency.  Then waits for a response.  And waits some more.  Meanwhile, the government’s delay in responding prevents the contractor from moving forward with some aspect of the project, causing the contractor to incur costs.

For contractors faced with this type of government inaction, a recent decision by the Armed Services Board of Contract Appeals is welcome news.  In that case, the ASBCA held that the government breached its implied duty of good faith and fair dealing by waiting more than three months to respond to the contractor’s request to amend the Statement of Work–allowing the contractor to “twist in the wind” during that period.

Continue reading

Not Reading the PWS is a Bad Idea, ASBCA Confirms

Here at SmallGovCon, we often write about nuanced, complex government contracting legal issues.  This isn’t one of them.

The moral of today’s story comes straight from the personal superhero files of Captain Obvious: not reading the performance work statement in your own contract is a pretty bad idea.

Continue reading

ASBCA: Under FAR, “Days” Meant Calendar Days, Not Business Days

The period of performance under a government contract, measured in “days,” meant calendar days–not business days, as the contractor contended.

In a recent decision, the Armed Services Board of Contract Appeals applied the FAR’s general definition of “days” in holding that a contractor had not met the contract’s performance schedule.

Continue reading

Release of Claims Can’t Be Undone by Refusing Government Payment

I recall sitting in a mediation one day when the mediator, a judge, told me and my client that we all have lightning in our fingers. He went on to explain that this means, once you sign a contract, it’s like magic in the sense that you can’t get out of the contract and are bound by it, absent certain exceptional circumstances.

I was reminded of this concept while reading a recent opinion from the Armed Services Board of Contract Appeals that dealt with the effect of a contractor signing a release with the government and then trying to back out of that release by refusing payment from the government.

Continue reading

GovConVoices: Prime Management Of Subcontracts: Will ASBCA Decision Affect DCAA’s “Obsession”?

The Armed Services Board of Contract Appeals recently dismissed a government claim that Lockheed Martin Integrated Systems, Inc. (LMIS), failed to comply with its prime contract terms by not adequately managing its subcontractors and therefore all subcontract costs (more than $100MM) were unallowable.

Although the government claim was directed at a large contractor, some of the amount in question, presumably, included invoiced amounts by small business subcontractors.  At least by implication, had the government prevailed, it could have resulted in requirements for prime contractors to become far more demanding and intrusive in terms of subcontractor documentation and/or access to subcontractor records.

Continue reading

ASBCA: No Valid Claim Certification Where “Signature” Was Typewritten

A contractor did not file a proper certified claim because the purported “signature” on the mandatory certification was typewritten in Lucinda Handwriting font.

A recent decision of the Armed Services Board of Contract Appeals highlights the importance of providing a fully-compliant certification in connection with all claims over $100,000–which includes, according to the ASBCA, the requirement for a verifiable signature.

Continue reading

Government Must Prove Amount Of Unilateral Price Reduction

While an agency may require a unilateral reduction in a contractor’s price due to a reduced scope of work, the government carries the burden of proving the amount.

In a recent decision, the Armed Services Board of Contract Appeals held that while an agency was entitled to unilaterally reduce the scope of work, the agency had not proven the amount of the unilateral deduction it demanded–and the government’s failure to meet its burden of proof entitled the contractor to the remaining contract price.

Continue reading